FAQ – Heavy Vehicle Industry

BRIDGE WORKS ARE NOW COMPLETED. All weight restrictions that were in place for our project have been lifted. Please refer to the National Heavy Vehicle Regulator for further advice.

Applicable information for freight businesses and/or operators of heavy vehicles weighing 42.5 tonne and above seeking access to the Phillip Island / San Remo bridge from 26 February 2024 until 6 February 2025.

  • Scaffolding works will occur from 26 February to mid-February 2025
  • Works will be conducted Monday to Friday 7am – 5pm, (excluding public holidays) and occasionally Saturdays.
  • Due to the use of suspended scaffold connected to the underside of the bridge, there will be no need to close lanes on the bridge to access the pipelines.
  • On rare occasions, traffic management or pilot vehicles may be required to enable bridge inspections, access for specialised heavy vehicles, and while navigational markers for marine users are relocated. This will mostly occur at night or early morning to minimise disruptions to traffic, occasionally lane closures of the bridge will occur during the day.

Works on the San Remo Bridge were completed on Thursday the 6th of February 2025.

For access on the 6/2/2025 and revised access from the 7/2/2025, please click here.

Please refer to NHVR Maps. for access limits before travelling. Heavy vehicle information will be removed from WPW website from COB 7/2/2025.

Updated 6 February 2025. 

  • Westernport Water has proactively advised known heavy vehicle operators that will be impacted by these limits.
  • Planning the journey of a heavy vehicle is the responsibility of the operator.
  • VMS signs being deployed will provide enough forewarning for those not already aware of the limit to undertake safe adjustment to their journey prior to approaching the bridge.
  • VMS signs have been deployed to provide advanced warning to those not already aware of the limit to undertake safe adjustments to their journey before approaching the bridge.
    VMS location mapThree VMS signs as per red crosses
  • Management of the product being carried, and ensuring the weight of the load complies with the general mass limit, is the responsibility of the operator and trips should be planned with the limit in mind.
  • The National Heavy Vehicle Register are responsible for compliance of general mass limits and will monitor compliance as part of their everyday compliance activities when working in the area.
  • The project commencement date was determined in October 2023, communications to the freight regarding mass limits commenced in late November 2023.
  • Due to the challenging nature of this project, its impacts and the required approvals to proceed, formal advice of the load limit was provided to heavy vehicle operators at Westernport Water’s earliest opportunity.
  • The heavy vehicle industry body has been engaged in the planning of this project throughout 2023.
  • Other solutions were considered by DTP to enable Westernport Water to deliver this important maintenance work, including traffic lights and a reduction to one lane, however this would have caused prolonged and significant impacts to all road users.
  • The scaffolding ensures the safety and stability of the bridge, while minimising impacts to the road network and road users.
  • To lessen the impacts as much as possible while these critical maintenance works are delivered, the mass limit of 42.5t was in place when construction projects typically ease.

There will be no impacts for emergency services access.

Westernport Water has liaised with local emergency services agencies, including Fire Rescue Victoria, SES and Parks Victoria. Each agency has confirmed that the bridge limits will not impact their local emergency response efforts.

There will be no impact to vehicles that are used to supply groceries, household goods, milk, petrol, and major events at the Phillip Island Gand Prix Circuit as they typically operate at or below 42.5t.

Operators can apply to the National Heavy Vehicle Regulator (NHVR) for a permit to access the bridge with a vehicle heavier than current weight limits. Access will be considered by NHVR on a case-by-case basis, dependent on time of day and traffic management conditions.

For example, the operator of a 5-axle mobile cane heavier than 42.5t that needs to cross the bridge for a job on Phillip Island can apply to NHVR for a permit. The operator will potentially get approval to cross the bridge with the conditions of closing the bridge to traffic during off-peak times, allowing only the 5-acle mobile crane to cross, (and nothing else).

Mass limits are necessary to protect the structural integrity of the bridge, ensuring the safety of all road users and contractors.

Trucks that are used to supply groceries, household goods, petrol, and events at the Phillip Island Grand Prix Circuit will not be affected as they typically carry loads of 42.5 tonnes or below.

Key links

Contact us

Please email bridgeproject@westernportwater.com.au or call 1300 720 711 if you would like more information about the project.

Updated 31 January 2025.